2017 North Main Street Bridge Rehabilitation

N Main Street Bridge Rehabilitation (Bridge Number 113/134)

General Information

Lead department: Engineering Department
Project manager: James Danis, Engineer
Funding: Tax Rate

Project Details

As part of the Town's ongoing effort to improve infrastructure the rehabilitation of the N Main Street Bridge over Spicket River will commence early in the 2017 Construction season. The project scope will (1) address scour concerns; (2) repair spalling and degradation of the structure headwalls; (3) reinforce bridge abutment/metal structure connection; and (4) 'chink' and re-grout the masonry portion of the structure. The rehabilitation effort will extend the service life of the bridge several years. The project is located on N Main Street just below the Walnut Terrace intersection.