December 2025 / January 2026 Update - Steel continues to be erected. Joists are installed and some metal deck is in place. Masonry of stairwell on right is still underway. Sallyport has been tented for masonry work to continue. Work has begun on some of the drainage ponds on site. Ductwork is being installed in the range.

October 6, 2025 Update - Construction of the walls for the first floor is well underway. You can see the windows starting to take shape along the east side of the building. The footings for the outbuilding have been poured and the foundation is formed. The foundation along with the slab for the sally port will be poured during the week of October 6th.

September 8, 2025 Update - Site work continues on the new PD project. The east side of the parking lot has been brought up to grade and a base coat of asphalt has been laid. The north half of the slab was poured on September 4th and the south portion will be poured the week of September 8th. The sally port and tactical training area have been brought up to grade. In this picture, you can see the layout of the future lobby area.

August 22, 2025 Update - The foundation of the main building is 100% complete. Crews are working on backfilling and bringing the slab floor up to grade. Underground plumbing and electrical infrastructure have been installed. Depicted in the photo is the foundation for the police department's first floor. The sally port is to the left of the building with the tactical training range to the rear. Site work will continue to bring the east side to final grade. The east side will be receiving a first layer of asphalt in September

July 10, 2025 Update - Work continues on the footings and foundation. This work should be completed by the week of July 21st. A majority of the footings and foundation for the building proper and range have been completed. Work on the sally port and outbuilding will begin in the next few weeks. Vertical construction should begin in early September.

June 6, 2025 Update - Demolition of the existing structure continued throughout the past week. The majority of construction debris has been safely packaged and prepared for proper disposal. Much of this material originated from the exterior of the original 1960s-era building, which contained asbestos in multiple areas and required careful handling. Portions of the original concrete slab still remain on site and are scheduled to be removed within the coming week. 

Meanwhile, foundation work has commenced on the north end of the site and is progressing eastward. This phase of construction is expected to continue over the next several weeks.

May 15, 2025 Update - It was a busy week at the Veterans Memorial site.  Demolition crews made quick work of the storage shed and K9 kennel. Demolition of the triple wide trailer was also completed followed by the beginning of the building proper.  The building tear down and clean up is expected to take three weeks.  The area of the main building which has been taken down housed the male and female lockers rooms, booking room, evidence storage and Special Services.  

May 2, 2025 Update - Abatement continues with much of the work being conducted in the building.  Some exterior bricks have been removed to gain access to detected hazardous materials.  Site work continues with drainage basins being constructed at the east and west entrances.  Fencing around the K9 kennel and impound lot has been removed.  The generator has been relocated and repurposed to the Municipal Services building at 21A Cross St.  Final utility cut off is expected the week of May 5th.  Building tear down to begin week of May 12th with a 3-week schedule.

April 18, 2025 Update - Site work continues with the removal of stumps and the erosion control has been completed.  The building at 9 Vets has been completely emptied as abatement begins.  The removal of hazardous material (asbestos) will take two-three weeks to complete.

April 11, 2025 Update - The Police Department successfully moved operations from 9 Veterans Memorial Parkway to the temporary space at 21A Cross St.  All police department operations will run out of this location until we move back to 9 Vets.  This is estimated to be late summer 2026.

Site work continues at 9 Vets with tree stumping and erosional control put in place.  Crews also installed the turtle bridges, a requirement from the State of NH to protect any turtles who may wander onto the site during construction.  

April 4, 2025 Update - Work is underway at 9 Veterans Memorial Parkway. Crews began site work on April 1, clearing land around the perimeter to expand the footprint. The existing building, shown in the photo, will be completely demolished to make way for a new facility.

Salem PD to Move to Temporary Facility Starting April 7, 2025


Starting on Monday, April 7th, the Salem Police Department will commence a phased movement of all police operations to a temporary facility.  The temporary facility is located at 21A Cross Street and will be co-located with the Town’s Municipal Services Department - Department of Public Works.

The Department expects to have completely transferred operations to the temporary facility by Thursday, April 10th, at which point, our current location at 9 Veterans Memorial Parkway will be closed for eventual tear down.  There will be signage directing people to the new location once the current location has closed.

Please click here for the full Press Release with more information.

Updated PD Rendering - Dec 2025

We are excited to present a comprehensive overview of our upcoming project—the construction of a new police station. This project is designed to enhance our community's safety and provide a modern and efficient space for our dedicated police force.

Project Details: The New Police Station encompasses an operational area on two levels of approximately 31,600 square feet and a Training Range of approximately 4,000 square feet. A K9 Outbuilding of approximately 4,000 square feet is located behind the building on the backside of the property. The overall layout is strategically situated within the existing footprint of the current Police Station. In total, the square footage of the new facilities will be approximately 40,000 square feet. This approach minimally impacts the wetlands, expedites the construction timeline, and allows our Police Department to function seamlessly during the building process.

Benefits of This Option:

  • Minimized impact on wetlands
  • Faster construction timeline (approximately sixteen months)
  • Uninterrupted Police Department operations
  • Complete separation from the public during construction

Project Breakdown:

  • Hard Costs: $29,740,462
  • Soft Costs: $3,549,702 (Totaling $33,290,164)
  • Relocation of Current Police Department and Owner's Contingency: $5,276,023

Total Project Cost: $38,566,188 

*See Project Budget Breakdown here*

Cost Per Square Foot: $951

Construction Period: Approximately sixteen (16) months

Important Note: To ensure the smooth execution of this project, we'll need to account for the relocation of the Police Department during the construction duration.

We are committed to transparency and community involvement throughout this process. For any questions or additional information, please feel free to reach out.

Thank you for your continued support as we work together to create a safer and more efficient future for our community.

Salem NH PD for Town Council 24.02.18_Page_09
Salem NH PD for Town Council 24.02.18_Page_11
425780349_18077398300447234_1663656376306891850_n
425749612_18077398309447234_789943243573303264_n
425703456_18077398318447234_8836902460291715041_n
425738785_18077398327447234_7403243616202534348_n
425706815_18077398336447234_2606567285460411015_n
425727714_18077398345447234_5725588635638776203_n
425717301_18077398354447234_4902235830535025488_n
425706900_18077398363447234_1371052354606388575_n
14
15
16
17
18
9
10
11
12
13

Building Today For a 
Safe and Secure Tomorrow!


Salem Residents Tour Sign Up Link Opens in new window

  1. Current Updates
  2. Project Background
  3. Events
  4. PR SCHEDULE
  1. Frequently Asked Questions (FAQs)
View All